Update from Ludford Grove

With the second fix complete on the detached home (the kitchen is being tiled today), focus has moved to the semi’s where the first fix carpentry is now complete. The last set of scaffolding will be coming down next week, and we are still on track for completing the build in September.

Work Continues apace!

Work Rolls On! The recent fine weather has been a big boost.  Windows are in the first pair of semi-detached homes, and with the roof on and solar panels installed the scaffolding was finally able to come down.  Inside Number 3 (see photo below) the first fix is underway and will be completed in the […]

Semi’s coming along nicely!

Windows arriving on Wednesday for the first pair of semi-detached homes. Roofing is well underway as you can see from the below pictures: